Cross project predecessorts not automatically calculating | Community
Skip to main content
Level 10
September 7, 2022
Solved

Cross project predecessorts not automatically calculating

  • September 7, 2022
  • 1 reply
  • 554 views

I am seeing that all cross project predecessors have stopped calculating and I have to recalculate timeline to get them to populate, under every circumstance. Is there a setting or something I should know about that would fix this? Otherwise I will open a support ticket.

 

Thanks

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by Kurt_Jones

There is a global setting under Setup->Project Preferences for recalculating timelines on regular basis

 

1 reply

Kurt_Jones
Community Advisor
Kurt_JonesCommunity AdvisorAccepted solution
Community Advisor
September 8, 2022

There is a global setting under Setup->Project Preferences for recalculating timelines on regular basis

 

JillAcAuthor
Level 10
September 29, 2022

Thanks for this, I did look at this and I would think that changing the predecessor would trigger the recalculation based on the 2nd check box, but it doesn't. I have to refresh the page in order for it to recalculate, every time.