Create Task report that shows next first open task if the previous task was completed with 100% | Community
Skip to main content
Level 2
August 26, 2024
Question

Create Task report that shows next first open task if the previous task was completed with 100%

  • August 26, 2024
  • 1 reply
  • 890 views

Can anyone help me to know how to create task report that shows next first open task if the previous task was completed with 100%

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

1 reply

JenL-LAZ
Level 2
August 27, 2024

It sounds like this may be a good starting point for the filters in your task report:

  • Task >> Can Start Equal True
  • Task >> Is Complete Equal False

Is there more that you want to see?

Level 2
August 28, 2024

Thanks for sharing.

Yes, we want to show only one task per project that is only when previous task should be completed with 100% and then we should show next task (one task per project).

JenL-LAZ
Level 2
August 28, 2024

If your workflow is pretty linear and you don't have multiple tasks with the same predecessor, I think those filters might do the trick.