hi
Im looking for some guidance for a project set up. I have costs against a user, however when when i create a tasks and assign them that to a user the Costs doesn't not show up in the report 😕
Views
Replies
Sign in to like this content
Total Likes
Hi,
Have you checked what cost type is associated with the task in the tasks finance settings? If you have a rate associated with the user's profile, the cost type will need to be 'user hourly'.
Regards,
Rich.