Hello,
Purpose is to highlight the task request that does not come at least 3 weeks in advance.
Thanks to blog entry from Kara (https://one.workfront.com/s/managed-content-blogs/workfront-wednesday-did-you-know-comparing-dates-and-more-with-conditional-forma-MCB64UAJFP6NGSFJ562WXWBB3S5Q) I got the comparison between plannedCompletionDate and entryDate to work.
It highlights red when plannedCompletionDate is less than entryDate, but it seems to ignore the +15d or +3w parts.
Reaching out to community and text mode wizards for help after many failed attempts to get this to work.
linkedname=direct
querysort=plannedCompletionDate
styledef.case.0.comparison.icon=false
styledef.case.0.comparison.leftmethod=plannedCompletionDate
styledef.case.0.comparison.lefttext=plannedCompletionDate
styledef.case.0.comparison.operator=lte
styledef.case.0.comparison.operatortype=date
styledef.case.0.comparison.rightmethod=entryDate
styledef.case.0.comparison.righttext=FIELD:entryDate+3w
styledef.case.0.comparison.trueproperty.0.name=bgcolor
styledef.case.0.comparison.trueproperty.0.value=eac6c9
styledef.case.0.comparison.truetext=
valuefield=plannedCompletionDate
valueformat=atDate
textmode=true
Thanks,
John
Solved! Go to Solution.
Topics help categorize Community content and increase your ability to discover relevant content.
Views
Replies
Total Likes
Hi Josh,
I don't believe this is possible. You would have to create a custom field with the calculation, then you can use that field as your comparison.