Comparing Actual Completion Date to Original Baseline Planned Completion Date
Hi All, I have a report that tells you the difference between the planned comp date and the actual comp date. This is the text mode used: displayname=Week Day Difference textmode=true valueexpression=WEEKDAYDIFF({plannedCompletionDate},{actualCompletionDate}) valueformat=HTML Wondering if there is a way to compare the actual completion date of the project with the planned completion date stored in the project baseline? Want to get a sense of how "far off" the project actually was, compared to how it was set up when it was flipped to current. Andrew Daniels Gartner, Inc.