Change due date colors if late

  • February 27, 2020
  • 1 reply
  • 474 views
Hi all, I'm trying to configure a view in a project where the 'due on' date will change to red if it's past the date. Here is what I have so far, but this is making all of the dates red. Can anyone help please? Elysia Yuen USANA
This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

1 reply

Level 2
February 27, 2020
Hi Elysia, Try "Planned Due Date is Less Than $$TODAY" - that should do the trick! (It's really weird to think of dates that way, but less than = before and greater than = after in Workfront in relation to dates.) Molly Privratsky Trendline Interactive