Capture % Complete on a specific date | Community
Skip to main content
KellieGardner
Community Advisor
Community Advisor
September 27, 2022
Solved

Capture % Complete on a specific date

  • September 27, 2022
  • 1 reply
  • 1012 views

I'm looking for a way to capture the percent complete of a task on a specific date. Trying to think through how to do a calculate field to capture this data. Wondering if anyone has ideas or has accomplished this?

 

#textmode #reporting

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by Doug_Den_Hoed__AtAppStore

 

Hi Kellie,

 

One out of the box approach would be to periodically a baseline of the Project(s) that contain such tasks, which would capture both the overall Project % Complete, and each underlying Task % Complete "on that date". With those in hand, were you to also mark the Baseline as default (or filter for the Baseline that matches "that date"), you can then pull the Task % Complete of interest. Taking Baselines is easy, but manual, so depending on how many and how often, I invite you to consider our Create Baselines solution, which can be scheduled (e.g. weekly) against a filter of those projects of interest (e.g. those with a status of "CUR").

 

Alternatively (albeit recklessly)...if all you really need is the % Complete on certain Tasks at a certain point in time, if you were to add a Custom Calculated parameter (e.g. "Latest Percent Complete") to (only) such Tasks, on the day you need Fresh Stats, you could:

 

  • BLANK the formula out and "Update Existing Data" to clear the old values,
  • (Recommended) examine a few samples to confirm the clear worked
  • UPDATE the formula (back) to =IF(ISBLANK({Latest Percent Complete}),{percentComplete},{Latest Percent Complete}) to "lock" the value on that date
  • (Recommended) examine a few samples to confirm the calculation worked
  • Report off the Latest Percent Complete as needed
  • Rinse and repeat as desired

If you decided to proceed with either, I'm interested to hear how it turned out (and curious as to why you chose the one you did).

 

Regards,

Doug

 

cc: note to self @doug_den_hoed__atappstore 

  •  

1 reply

Doug_Den_Hoed__AtAppStore
Community Advisor
Doug_Den_Hoed__AtAppStoreCommunity AdvisorAccepted solution
Community Advisor
September 27, 2022

 

Hi Kellie,

 

One out of the box approach would be to periodically a baseline of the Project(s) that contain such tasks, which would capture both the overall Project % Complete, and each underlying Task % Complete "on that date". With those in hand, were you to also mark the Baseline as default (or filter for the Baseline that matches "that date"), you can then pull the Task % Complete of interest. Taking Baselines is easy, but manual, so depending on how many and how often, I invite you to consider our Create Baselines solution, which can be scheduled (e.g. weekly) against a filter of those projects of interest (e.g. those with a status of "CUR").

 

Alternatively (albeit recklessly)...if all you really need is the % Complete on certain Tasks at a certain point in time, if you were to add a Custom Calculated parameter (e.g. "Latest Percent Complete") to (only) such Tasks, on the day you need Fresh Stats, you could:

 

  • BLANK the formula out and "Update Existing Data" to clear the old values,
  • (Recommended) examine a few samples to confirm the clear worked
  • UPDATE the formula (back) to =IF(ISBLANK({Latest Percent Complete}),{percentComplete},{Latest Percent Complete}) to "lock" the value on that date
  • (Recommended) examine a few samples to confirm the calculation worked
  • Report off the Latest Percent Complete as needed
  • Rinse and repeat as desired

If you decided to proceed with either, I'm interested to hear how it turned out (and curious as to why you chose the one you did).

 

Regards,

Doug

 

cc: note to self @doug_den_hoed__atappstore 

  •  
Doug_Den_Hoed__AtAppStore
Community Advisor
Community Advisor
September 28, 2022

 

Thanks Kellie!

 

I'm pleased that [correction] calculated parameter approach was of use to you, and appreciate you marking it as best answer. in doing so, you just wished for three more wishes. 😉

 

Regards,

Doug