Can you edit a project's actual completion date?
I remember being able to edit the project's actual completion date in the past, but I can't seem to find a way to edit it now. The help article linked below says that you can do this through the Project Details tab. I also tried creating a project report showing the Actual Completion Date field and I wasn't able to edit it there as well. I am able to edit a task's and issue's actual completion date once they are closed, but not projects. We use reporting to tracking the total duration of projects. However, if a person forgets to close their project on time, we want to be able to set the completion date the correct date. Does anyone know a way to edit the project's actual completion date? https://experience.workfront.com/s/article/Understanding-the-Actual-Completion-Date-of-a-Project-432597313 Denver Lemont Cardinal Health