Hi - can you provide more details? If we know people are not going to be working on the project, we utilize lag. So for example, when we send to client, the Feedback Due task has a predecessor but with 5d lag as it usually takes a week to get the feedback back from the client. That way things will reflow when there are changes earlier in the project, but that week is free for the team members.