Can you adjust the assignee's allocation in a task so you can assign 2 people to one task and have the work divided the way I want it- i.e Art director- 5%- Designer 95%.
Can you adjust the assignee's allocation in a task so you can assign 2 people to one task and have the work divided the way I want it- i.e Art director- 5%- Designer 95%. I want both to be aware of the timelines and due dates but don't have to have individual tasks.
This is already available under [select task] » Edit » Assignments.
Just be aware that like the task itself, the percentage split is not a hard split: the system will do nothing to stop any assigned party from going over-allocation/budget.