I suspect (valid) resistance from PMs instructed to manually adjust a certain task to always end on a Tuesday (particularly if your plans then shift enough to negate that change), so instead, invite you to (buckle up and) consider:
- creating a Schedule called "Tuesday Only", with only business hours on Tuesdays enabed
- creating a User called "Tuesday Bot" (or something similar), to which you'd then assign the "Tuesday Only" schedule
- assign that Tuesday Bot user as the Primary Assignee on those tasks in your Projects (and if you like this approach, eventually in your templates) but with zero percent on the task (and/or perhaps, a zero FTE on the user...if possible; untested)
By doing so, if I'm imagining correctly, and assuming the task in question is <1 day in duration (trickier otherwise), Workfront will recognize the Tuesday Bot for that task as the primary assignee, and then look to it's schedule (Tuesdays Only) to schedule the work, and as a result, automatically "bump" the planned date to the first available Tuesday...even when your plans change, with no extra work on behalf of the PMs.
Regards,
Doug