Can I determine turnaround time with just the dates (without including the time)? Example: I want to know if something was completed by 3/15, but it is showing late if it was closed after 5:00 pm on 3/15. | Community
Skip to main content
Level 3
April 19, 2022
Question

Can I determine turnaround time with just the dates (without including the time)? Example: I want to know if something was completed by 3/15, but it is showing late if it was closed after 5:00 pm on 3/15.

  • April 19, 2022
  • 1 reply
  • 629 views

My Formula: IF(Actual Completion Date>=Planned Completion Date,"Late","Good")

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

1 reply

KendraRo2Author
Level 3
April 19, 2022

I had not. Thank you for the tip.