Expand my Community achievements bar.

Calculating Actual cost

Avatar

Former Community Member
Hello Everyone, I am having trouble getting the actual cost for my hours report. I have the role name and billing hour cost set up but it is not calculating. Can someone assist me with this? Thank you, Chandra Chandra Savage 1-800-FLOWERS.COM, Inc.
Topics

Topics help categorize Community content and increase your ability to discover relevant content.

5 Replies

Avatar

Level 10
Are your tasks set up to calculate based on user or role cost? Michael Lebowitz Marketing Analyst Michael.Lebowitz@guidewellconnect.com T 904-436-4240 | M 904-200-1364 Fax 904-565-6156 4800 Deerwood Campus Pkwy DCC 800-4-272 Jacksonville, FL 32246

Avatar

Level 10
Are those task set up as Billable ? Dagmara Garwell BAKKAVOR LTD

Avatar

Former Community Member
Hello Everyone, I have the billing cost set up per user in their profile. Chandra Savage 1-800-FLOWERS.COM, Inc.

Avatar

Level 8
On the finance settings on the task, do you have Cost Type set to User Hourly? Adina Pierce Cisco

Avatar

Level 10
Have you tried using the recalculate finance option on the Project? Seems like when we started using Costs, which we did after-the-fact, I had to bulk edit the Cost Type on all of my Tasks for existing projects to "User Hourly". I had to do this because previously we didn't have a value set in the overall configuration. Then I had to use the recalculate finance option. This forced the Costs to update on all my tasks. Admin Kelly-Wehrmann SSFCU