Bulk Edit Task Planned Start Date

Avatar

Level 2

Besides Fusion, does anyone know of a way to bulk edit the planned start date on Tasks?

I have tried in the timeline and in a report. In both places only the actual dates are on option to edit.

Thanks!

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Accepted Solution

Avatar

Correct answer by
Level 10

Hello Michael,

 

Before being able to bulk edit planned start dates on task, you need to make sure, that all tasks are set to a task constraint, which allows editing the planned start date.

 

If you select multiple  tasks and click on edit, changing the Task constraint to e.g. "Fixed Dates" will provide you with the possibility to change the planned start & end date. 

 

Regards

Lars

View solution in original post

2 Replies

Avatar

Correct answer by
Level 10

Hello Michael,

 

Before being able to bulk edit planned start dates on task, you need to make sure, that all tasks are set to a task constraint, which allows editing the planned start date.

 

If you select multiple  tasks and click on edit, changing the Task constraint to e.g. "Fixed Dates" will provide you with the possibility to change the planned start & end date. 

 

Regards

Lars

Avatar

Level 2

Thank You! Changing the constraint did make the field appear.