Behavior and notifications for tasks assigned to teams
I need some help understanding how to structure a workflow for teams that self-assign work. I'm trying to set up a process where when Task A is completed, the Design Team gets notified that Task B is ready to start. Somebody from the Design Team would then assign the task to themself along with the rest of the tasks in that project for the Design role.
I've tried experimenting with assigning tasks to teams in Workfront, but it seems like the team only gets notified when the project is activated and they do NOT get notified when any task predecessors are complete.
How would I build this in Workfront?