Question
Baseline Task report
Hi I am in desperate need to figure out how to report on tasks Baseline vs Actual. I have the setup to automatically create a baseline for every project and include it in all templates. Yet, I can't seem to get a report by Task. I've tried searching everywhere, I've tried to create a Baseline Report, I've tried some custom columns that are found in the Help section, none of this is giving me what I need to see where tasks are slipping and who is responsible for those tasks. Very simply what I want is this: when a project turns from Planned to Current the baseline should be set for all tasks in the project. Then I want a report with these columns: Filter by Portfolio + Status=Complete Columns: Project Name Task Name Planned Completion Date from the Baseline Actual Completion Date Assigned To: Name Any help I could get on this would be huge for me. Thanks! Jill Ackerman