Automatic Task Duration?

Avatar

Level 4

Is there a way to make the Duration of a task be automatically set to begin at the due date of the previous task and end at the current task due date?

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

3 Replies

Avatar

Level 5

Check out the Task Tracking Mode "Predecessor" It might do what you're looking for.

Avatar

Community Advisor

Avatar

Employee

Thank you for sharing these, Heather!