Hello Friends,

I have a question, in Microsoft Project software, I can set the project calendar excluding the holidays, so the tasks will not be fell into this timeframe,

but in Workfront, how can I set this calendar? or by other methods of setting holiday tasks? Please help advise. Thanks!

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by AndyKent

@jerrywu 

Go to the project settings and you'll see 'User Time Off'. There's a couple of options, either 'Consider' or 'Ignore'.

2 replies

AndyKent
AndyKentAccepted solution
Level 2
February 19, 2024

@jerrywu 

Go to the project settings and you'll see 'User Time Off'. There's a couple of options, either 'Consider' or 'Ignore'.

JerryWuAuthor
Level 2
February 26, 2024

Thanks AndyKent, appreciate your help! very helpful! 

skyehansen
Community Advisor
February 19, 2024
JerryWuAuthor
Level 2
February 26, 2024

See you again, you are the expert! Really appreciate it, thank you very much!

JerryWuAuthor
Level 2
February 26, 2024

I am working with system admin team to fix it.