Are any of you having an issue with not being able to see the task duration on the Home view of the new experience.
If your workers are looking at a task and only see it as due on Friday, how do they know if it is actually a 5 day task and they need to start working on it on Monday? Has anyone figured out a work around for this? I would love for the Home calendar to show a task spanning from Monday-Friday if it is a 5 day duration task.