Agile_Iteration duration_calculation | Community
Skip to main content
September 25, 2022
Question

Agile_Iteration duration_calculation

  • September 25, 2022
  • 0 replies
  • 341 views

when I set up a Iteration for 2 weeks ( meaning 10 working days ) then why i see in project plan it is 9,38 days or more or less and not 10 days. If you can please help with the formula behind. 

Thanks for assisting . 

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.