What is the best way to account for department and corporate events in project timelines? I am tempted to have everyone in the department enter "time off" for the two day department events that occur one time per quarter but wanted to check to see if anyone has a better idea. It know it will work, but don't want to pass up an option I am not aware of.
Views
Replies
Total Likes
what would you think about adding it to the schedule as a "holiday"?
Views
Replies
Total Likes
Considered that but it does not impact all departments just 2, which is a subset of the project team.
Views
Replies
Total Likes
oh bummer... yeah OOO would be your next best option. If you had fusion or if you wanted to do it via an API call, you could implant it for the whole dept, but failing that, everyone would have to manually enter.