Workload Balancer - late unassigned work

Avatar

Level 5

3/26/21

This is a HUGE problem for us. Unlike the assigned work, the unassigned work section of the Workload Balancer will not display Projected Dates. Therefore, if work is not assigned and the Planned Dates are no longer in the range that the resource manager is viewing, it is forgotten. There needs to be a better way for managing late work as there will always be late work.

1 Comment

Avatar

Level 5

4/12/21

We usea report/dashboard to track late and unassigned tasks. PMs review it weekly to address the issues and can filter it by project type and date range.