Working On and Scheduling views: Show hours on Unassigned Tasks "swimlane"

  • February 12, 2018
  • 2 replies
  • 358 views

Hi,

It would be VERY useful to be able to see the hours (by day) of the unassigned tasks on the Working On and Scheduling views. Currently only the total hours for assigned tasks are shown, but not for unassigned tasks (see screenshot).

I think the above is an incomplete picture. You not only want to see the allocated hours (and the remaining capacity) but also the (unassigned task-)hours that you need to move to those people

2 replies

StephenEvAuthor
Level 2
March 15, 2018

Small addendum to this idea. Actually the hours would ideally be presented at task AND total levels (per day).

Currently the tasks have to be expanded to see the hours, which perhaps makes sense for the assigned tasks, but when reviewing the unassigned tasks it would be nice if the information was more readily available/presented.

Something like...

Kelly_Wehrmann
Level 9
May 8, 2018

Agreed, but let me add a twist. Our PM has asked if the UI could be updated so that when you hover over the portion of the bar that shows the planned work, that the hours per day would display so you didn't always have to expand the task to see the allocations for that resource.