Slack Date
The slack date field in Workfront should calculate correctly. This would allow you to see how close a task is to critical path. Currently, Slack Date will equal the projected completion date if the task has successors. This happens with both critical and non-critical tasks. It does not work as described on Workfront’s support site.
https://support.workfront.com/hc/en-us/articles/216636478-Understanding-Slack-Date
In the example below, Task B should have a different slack date. The task is not on critical path and can be delayed 5 days before impacting Task D.
|
Task# |
Task |
Duration |
Predecessors |
Planned Start |
Planned Comp |
Projected Start |
Projected Comp |
Slack Date |
Is Critical |
|
1 |
1 Day |
|
3/23/17 |
3/23/17 |
3/23/17 |
3/24/17 |
3/24/17 |
True | |
|
2 |
5 Days |
1 |
3/24/17 |
3/30/17 |
3/24/17 |
3/31/17 |
3/31/17 |
False | |
|
3 |
10 Days |
1 |
3/24/17 |
4/6/17 |
3/24/17 |
4/7/17 |
4/7/17 |
True | |
|
4 |
1 Day |
2, 3 |
4/7/17 |
4/7/17 |
4/7/17 |
4/10/17 |
4/10/17 |
True |