MyWork: Ability To Distinguish Tasks Where Predecessor Has Been Completed Vs Pending Task

  • October 25, 2018
  • 2 replies
  • 489 views

We are trying to use predecessors to automate tasks from one step to the next. However, the resource user cannot distinguish tasks where the predecessor has been completed so they can start their task. Currently when going to "Ready to Start", the tab has also included tasks in which the predecessor is still pending.

2 replies

October 30, 2018

I agree that this feature would be very beneficial for our teams as well!

Our developers have many tasks in their work lists marked as "Ready to start" even if the actual predecessor tasks have not been completed.

imgrund
Adobe Employee
Adobe Employee
December 3, 2018

So late to the game, but shouldn't this already be in effect? The support site says that something is only Ready To Start when there are no predecessors stopping it? https://support.workfront.com/hc/en-us/articles/228271868-Understanding-Work-Requests

Have you put in a ticket? I can put one in too so that they see it is an issue everyone is facing.