Automatically attach parent task milestone to the child tasks

  • May 2, 2023
  • 1 reply
  • 460 views

I'd like to see parent tasks automatically attach the milestones to the child tasks.

We need reporting to pull all tasks associated with a milestone phase to see summary duration, planned hours, actual hours on all tasks under that Milestone regardless of the Parent Task Name or Project Name.  

Currently, the milestone only is can only relate to one task.

1 reply

KristenS_WF
Level 7
May 3, 2023

It's not automatic, but I'm able to pull all child tasks for a given milestone using this filter (with line 3 giving the object ID of the milestone in question):

 

numberOfChildren=0
numberOfChildren_Mod=eq
parent:milestoneID=63ef9d16001f2d313ba32cecd9d2867f
parent:milestoneID_Mod=in