Update a specific task end date for a group of projects using Fusion
Hi folks. I have a scenario that is creating a set of projects based on 1 of 4 templates based on filters, and I'm setting the overall project end date based on a campaign end date plus x days so the workflow can also build in x weeks to turn around post-campaign analysis.
However the launch date of the campaign could be anything from a day to 6 weeks before the campaign end date, and I need the tasks preceding launch to back-calculate their dates (based on predecessors & successors) from the launch date. The launch date for each campaign is specified in the original doc I'm linking to, but is there a way to update my "launch campaign" task in all created projects to have a planned completion date based on the corresponding date in the source file?
That reads back quite complicated to me, so a more simple clear would be "has anyone successfully used Fusion to update the planned completion date for a specific task across a number of projects"? 🙂
Thanks in advance for any help!