Module(s) to filter most recent projected completion date

Avatar

Level 1

I'm sure there's an easy way to do this that I haven't explored. I have a scenario where I set up an API call to pull recently completed tasks for a project. I want to filter the most recent completed tasks so it pinpoints a single task vs. multiple. Is there a module I can set up to take the projected completion date from my API call and and pull the task that is closest to today? 

API Call Module.png

1 Reply

Avatar

Level 1

I was able to figure out a solution by creating a search task and filter for the Projected Completion Date that was greater than or equal to anything that happened in the last 5 minutes. 