[Fusion] Moving A Task To The End of A Project Using Fusion | Community
Skip to main content
Eric_D_Miller
Level 5
January 2, 2025
Solved

[Fusion] Moving A Task To The End of A Project Using Fusion

  • January 2, 2025
  • 1 reply
  • 475 views

I am running a scenario that copies a set of Template Tasks over to a project after it's initial creation, but the last task of the Template Tasks I am copying over is excluded as I only need that task once in the project. Currently after flipping my project I am left with that has that "end/last" task, but it lands earlier in the timeline than it should (due to the original project conversion and subsequent Template Tasks being added later in the scenario).

Is there a way to target an individual task on a project and then set that task as the last task in the project?

Any help is greatly appreciated! 

 

Thank you,

Eric

Best answer by Eric_D_Miller

I figured it out by doing a search on the project for the task with the specific name (my end task). After I got the ID of that task I used the Misc action to move the task to the same project it was already in, leaving the parent task field blank.

 

Seemed to work fine! Will post any updates if I see any issues.

1 reply

Eric_D_Miller
Eric_D_MillerAuthorAccepted solution
Level 5
January 2, 2025

I figured it out by doing a search on the project for the task with the specific name (my end task). After I got the ID of that task I used the Misc action to move the task to the same project it was already in, leaving the parent task field blank.

 

Seemed to work fine! Will post any updates if I see any issues.