Cannot change Task Planned Duration
Hello,
I'm working with a project with several tasks that have 10,000 Days as a Planned Duration. The project is set to Complete with a Planned Start Date of 8/4/17 and a Planned Completion Date of 1/1/20. The Task Settings are: Task Constraint= ASAP, Commit Date = 1/1/20, Planned Completion Date=9/30/24, Act. Start Date=1/1/20, Actual Completion Date =9/30/24, Duration Type = Calculated Assignment with a Duration of 1960 Days and 650 hours. The Projected Completion Date is 2/22/2063. The task is a parent task. There are no predecessors assigned to the task.
Could someone tell me how to change the task's planned duration to something less than 10,000 days? I cannot update the field.


