Hi all,
Can we Shift the date of a Scheduled Campaign in running state?
Thank you.
Solved! Go to Solution.
Hi Gunjans6748888,
To answer your question, In order to modify the date, you need to stop and change the date, after which you have to start it again.
Unfortunately, you cannot change the date of a running campaign.
Hope this is of some help
Filip
Hi Gunjans6748888,
To answer your question, In order to modify the date, you need to stop and change the date, after which you have to start it again.
Unfortunately, you cannot change the date of a running campaign.
Hope this is of some help