내 커뮤니티 업적 표시줄을 확대합니다.

Submissions are now open for the 2026 Adobe Experience Maker Awards

Mark Solution

활동이 없어 이 대화는 잠겼습니다. 새 게시물을 작성해 주세요.

Difference between actual start and actual completion date of task

Avatar

Level 1

Hi,

 

I am trying to see the no of days between a task's actual completion vs actual start. I wrote the query like this. But it is not giving me any result.

displayname=Difference
textmode=true
valueexpression=WEEKDAYDIFF({actualCompletionDate},{actualStartDate}) valueformat=HTML

1 답변 개

Avatar

Level 2

Were you able to get this resolved?  I'm trying to do the same thing.  I am looking to have a column that will give me the number of days and time between the actual start date of a task and the actual completion date.  Text mode and I don't get along all the time so if someone has the actual code i can copy and paste that would be amaizing.