Workflows going to finished state without processing.
We use an on-premise instance to access adobe campaign classic V7 build 9349. Lately, we have seen almost all the workflows going to the finished state without processing. The workflow on schedule or an external signal just starts upon a trigger or on schedule and goes to the finished state. This happened when we were using build 8860, and upon suggestion from Adobe, we upgraded the build in July 2022 to use 9349, but still the issue persisted.
Can you suggest if a retry mechanism can be added to the workflows if it goes to a finished state to have it restarted automatically without manually restarting it?
We need help resolving the issue as many of the campaigns are on schedule, and the marketing communications should go as scheduled.
Note: This happens with all our workflows (Techincal workflows/Business campaigns/ Out of box workflows (Ex: Campaign Jobs, Offer Notification, etc.)
Thanks,
Maliha