We have a few tasks that happen on a Planned project before it moves to Current. Because tasks on a project in Planning don't show on the Lion/homepage we created a report that shows planned tasks two weeks out. | Community
Skip to main content
Level 3
April 13, 2022
Question

We have a few tasks that happen on a Planned project before it moves to Current. Because tasks on a project in Planning don't show on the Lion/homepage we created a report that shows planned tasks two weeks out.

  • April 13, 2022
  • 1 reply
  • 855 views

The challenge we have is that these tasks have multiple resources on them. So even if a resource marks their part complete it will show in their report until all resources mark their part complete. I have a filter that says dont show completed tasks but that task wont show completed until all resources mark their part done. Any ideas for filters or reporting features that will make this task disappear after the user has completed their part even if the other resources havent yet?

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

1 reply

Level 10
April 18, 2022

We had this problem when we first deployed. Sounds like you are using a Task report, where you need to use an Assignment report.

HeidiS1Author
Level 3
April 19, 2022

Very cool. Do I just look up Assignment Report? I wasnt aware of them. Any tips for setting up an assignment report. What is the difference?

HeidiS1Author
Level 3
April 20, 2022

wonderful. thanks so much