Question
Tasks Late/Incomplete vs. Total Tasks Assigned
Good morning WF geniuses, I'm trying to setup a report that shows tasks that a user is assigned to that are late (either alone, or part of multiple people) that are not yet complete. I'd like to show this against the total tasks assigned to them. So for example, if Gina is showing she has 30 tasks late that are incomplete it seems alot. However, if its 30 out of 300 total tasks it's a different perspective as it's only 10%. Ultimately I'm trying to chart that 10%/90% in a visual way for management. I thought the assignment report might be the best route, however, I'm at a loss how to summarize the total vs. incomplete that are late. Anyone have something similar? Thanks in advance! Christina