Report all child tasks is user is assigned to one of the child tasks

  • March 12, 2020
  • 5 replies
  • 868 views
Hi All: I am trying to create a report that returns all the child tasks of a parent task if the user is assigned to any one of those child tasks. For instance, we have a project with 200 parent tasks that each have the following child tasks 1) Prepare 2) Review 3) Address Comments and 4) Final Sign off. I want to create a chart that groups all the child tasks of that parent by status if the user is assigned to any one of the child tasks. Has anyone been able to create something similar? Regards, Brandy Brandy Johnson John Hancock Investment Management
This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

5 replies

imgrund
Adobe Employee
Adobe Employee
March 12, 2020
Hi - you will want to make sure you use the filter Assignment Users ID equals $$USER.ID. If you use Assigned To ID that only brings back tasks that they are task owner on. (SIDE NOTE: If you are ever looking for a role that is assigned to tasks on a project, you want to use the Assignment Roles ID equals filter, not Assigned To Role ID equals) Hope that helps. Anthony Imgrund FCB
Level 2
March 12, 2020
Hi Anthony. Thank you for your response. I don't think that is quite what I'm looking for. I am looking to pull all child tasks related to a parent task even though the user is assigned to only one of those child tasks. For instance: Parent Task 1 - no assignment child task 1 - assigned to user 1 child task 2 - assigned to user 2 child task 3 - assigned to user 1 and user 2 child task 4 - assigned to user 2 Parent Task 2 - no assignment child task 1 - assigned to user 3 child task 2 - assigned to user 2 child task 3 - assigned to user 3 and user 2 child task 4 - assigned to user 2 If user 1 runs the report, I want all 4 child tasks associated with Parent Task 1 to return. If user 2 runs the report, I want all 8 of the listed child tasks to return. Do you have any suggestions for this scenario? Thanks, Brandy Brandy Johnson Manulife - John Hancock
Doug_Den_Hoed__AtAppStore
Community Advisor
Community Advisor
March 13, 2020
Hi Brandy, I've been giving your requirements some thought today. Pretty tough one -- perhaps even not possible -- using Workfront's standard reporting. Best guess, in theory, with no testing, and admitting that I might be overthinking it, this might have a shot: create a custom parameter that records a) for each Child node task's (i.e. "Number of Children = 0") Parent ID in it, or b) for Parent Tasks, it's own ID create an EXISTS that finds every such custom parameter where the Tasks is assigned to the logged in user ($$USER), using Anthony's tip above apply that EXISTS against a Task Report that joins on that custom parameter If that's too much, though, I'd invite you to consider our "https://store.atappstore.com/product/magic-reports/" Magic Reports offering, if the benefit warrants so. Regards, Doug Doug Den Hoed - AtAppStore
Level 2
March 16, 2020
Thanks for the help, Anthony & Doug! I got it to work by using the following filter: EXISTS:a:$$EXISTSMOD=EXISTS EXISTS:a:$$OBJCODE=TASK EXISTS:a:assignmentsUsersMM:ID=$$USER.ID EXISTS:a:parentID=FIELD:parentID Brandy Johnson Manulife - John Hancock
Doug_Den_Hoed__AtAppStore
Community Advisor
Community Advisor
March 16, 2020
You Rock, Brandy: well done! Regards, Doug Doug Den Hoed - AtAppStore