Project report showing projects NOT having a milestone task
Hi Workfront Community,
I'm looking for a solution that might be a little bit complex but your suggestions to achieve this are welcome. To be honest we are struggling to get something which looks very simple.
So.. we want to track projects that do NOT have a milestone linked on any of its tasks list. Example: Let's say we have Initiation, Design, Delivery and Go-Live milestones on a milestone path. I'm trying to identify projects that do not have "Go-Live" linked on its tasks. We want to make adding "Go-Live" as a mandate for our PMs to produce KPIs.
I believe we'll have to use 'collections' here because referencing does not work down the object hierarchy.
Thanks!