Hi 

I am fairly new to WF so still trying to navigate through all the tutorials etc 🙂

I have started created tasks, however I do not have the Indent/un-indent icon doesn't exist and when I right click on a task it doesn't show up there either. I have been set up as a System Administrator however, this has been racking my brain as to why I cant indent/unindent my tasks.

I can see my subtasks when I click on the parent task > then click on sub tasks. But it would be great to see the highlighted parent task/milestone and the indented child tasks.

 

Any suggestions would be great!

Thank you all.

Este tema ha sido cerrado para respuestas.

3 respuestas

Level 2
August 16, 2022

Hello,

 

Is it possible to check that all the Tasks are still in order by clicking into the grey column header above tasks with a hash mark & arrow? Clicking in here restores the correct order which can get mixed up when you are setting up & moving tasks about.

 

Another area to check is if you have a Filter, View or Grouping in use as this can also prevent the parent/child tasks displaying as expected and removes the options to indent when you right click etc

 

Hope this helps!

Level 5
August 16, 2022

Be sure that your task list is showing in numerical order, otherwise you can't see the indents.

Level 4
August 16, 2022

Came here to second Stacey's note. Fought this for a bit with some task reports when I first started. 

August 30, 2022

I discovered that the indent/outdent icon appeared once I took it out of Planning status.