Option to enforce predecessor completion check in case of task autocomplete | Adobe Higher Education
Skip to main content
Level 3
April 5, 2018
New

Option to enforce predecessor completion check in case of task autocomplete

  • April 5, 2018
  • 2 respostas
  • 386 Visualizações

Request:

Provide an improvement (maybe as option) to check predecessor status when autocomplete tasks. Current implementation considers only planned dates.

Use Case:

If Task 1 (due on 1/1/2018, tracking mode "User Must Update") is a predecessor of Task 2 (due on 1/1/2018, duration 0, tracking mode "Auto Complete") if Task 1 slips, the current implementation would close Task 2 but Task 1 would show late. What seems more useful is that Task 2 would not close until Task 1 is closed even in the event of a slip in Task 1.

2 Respostas

Heather_Kulbacki
Community Advisor
Community Advisor
December 10, 2019

This would be very helpful. It seems a miss that a task auto-completes based on date alone and no other factors are taken into consideration.

JamesHill_ATL
Level 3
January 22, 2020

Agree - this would be helpful!