New Resource planner (Total planned By user) | Community
Skip to main content
August 23, 2018
New

New Resource planner (Total planned By user)

  • August 23, 2018
  • 1 reply
  • 312 views

Trying to test the new resource planner tool (to replace the legacy planner tool that will be decommisionned soon) ...

When running the tool by User, why TOTAL PLANNED HOURS by USER are those of all projects status ?? This is a problem with "On__HOLD" projects where planned hours are still set on the period. These hours should be excluded from the total planned (because it's no more an active charge for the user).

1 reply

Level 3
August 24, 2018

I think the answer is yes to your question. There is another idea post to allow filtering by project status.

https://support.workfront.com/hc/en-us/community/posts/360014653333-Subtract-allocation-and-availability-data-when-filtered-out-of-Resource-Planner