Is there a way not to allow time to be logged to tasks that are marked as complete. thanksShawn

  • August 19, 2020
  • 1 reply
  • 756 views

Is there a way not to allow time to be logged to tasks that are marked as complete.

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

1 reply

Level 4
August 20, 2020

@Shawn Flege‚ - I know you can stop users from logging time on completed/dead projects from setting that in the preferences area but it does not look like you can stop users from logging time on completed tasks. 😔 If this is something that is happening, you can probably build a report that shows the date the task was closed and add filters to show time logged after the "actual completion date".

Here is the article that mentions you cannot stop users from logging time on completed tasks or issues: https://one.workfront.com/s/article/Timesheet-and-hour-preferences-515667443

Hope this helps.

Erica

Adobe Employee
August 20, 2020

Erica nailed it. It can only be done at the project level.

Once a project is complete, you can modify the life after death settings in Setup -> Timesheets & Hours -> Preferences -> Log time on projects that are complete.