How to efficiently do Hour Allocation in Workload Balancer?
Hello together,
we have just introduced the Workload Balancer to help our Teamleader to allocate Hours for Tasks/Issues for 4 People.
- Issues take from Creation to Completion on average 60 - 90 Days with different Amount of Hours
- Project Tasks have a Duration of 14 Days with 20 Hours each (I have set the 20 Hours in the Project Template).
-> That means in The Workload Planner automatically for Project tasks every Day 1.6 hours are allocated, for Issues around 0.08 Hours per Day.
How do I in a fast Way adjust Allocations to be realistic? I could go ahead and manually set
- 10 Days on 0 Hours; 4 Days on 8 Hours for Tasks
- 55 Days on 0 Hours; 5 Days on 8 Hours for Issues
but that is very tidious Work.
Ideally I would like as a standard to have the balancer set the Hours from the last Day Backwards for as many full days as needed. I already have a global Simple Duration set, that didnt help.
Is anyone able to share their Knowledge or Experience? Thank you, Leonhard