Question
How is duration calculated?
Hi All- this seems like a silly question- but my PM's are obsessing about it- how is duration calculated? I know it depends on the task settings- let's assume it's a calculated assignment, and as sson as possible (we're still learning how to leverage all these settings)
i.e-
task duration 10/1-10/2 (in WF is 1 day, but in our previous system- counted as 2 days.
task duration monday through friday (in WF is 4 days, but in our previous system counted as 5 days.
The rational I come up with is- Monday to Tuesday is 1 day, Tuesday to Wednesday is 1 day- and so on.
Is that the correct way to explain it to the pm's? And also- if the duration is SAME day- do you all put 0 days to make sure the dates stay on the same day?
i.e- task starts 10/1 and finishes 10/1- duration = 0 days? or do you put .5 days?
Part two:
if we have a project- that isn't really going to leverage predecessors, so they're bascially going to hard code the dates- what are the best settings for the task? i.e- duration type and constraint type?
thanks in advance for any insight!
Karen
tks
Karen