Durations and Resource Planner | Community
Skip to main content
Lauren_McCollim
Level 2
November 18, 2019
Question

Durations and Resource Planner

  • November 18, 2019
  • 13 replies
  • 1727 views
I am noticing that it seems that if we have a 0 duration for a task (needs to be done the same day) that the planned hours for the work are not showing up in the resource planner for the person assigned to them. Have you all noticed this before? Do you know what is going on? Lauren McCollim, M.B.A, PMP Advertising Project Manager Pensacola Christian College
This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

13 replies

Lauren_McCollim
Level 2
November 19, 2019
So what seems to be working is if i match the duration to the planned hours - if it's 0.08 hours of work, then i make it a duration of 0.08 hours. Lauren McCollim, M.B.A, PMP Advertising Project Manager Pensacola Christian College
Heather_Kulbacki
Community Advisor
Community Advisor
November 19, 2019
We ran into that quite awhile ago and were told it's working as designed - although I don't know the specific reasoning, someone else on my team worked on that ticket. Our workaround is to duplicate whatever is in the planned hours column in the duration column, so if it's 0 days and 1.5 hours, we change the duration to 1.5 H as well.
Lauren_McCollim
Level 2
November 19, 2019
Heather, I think that is what we are going to do here. It seems like that is working from the testing i have done. Thanks for much for letting me know! It gives me confidence knowing what I'm thinking is what you all have tried and had success with. Thanks again! Lauren McCollim, M.B.A, PMP Advertising Project Manager Pensacola Christian College