Hi Community!

Over the past few weeks my team has noticed issues with condition status(At risk, In trouble, etc.) The condition status on projects aren't updating automatically. An update must be posted for the condition status to change. 

 

Example: Project with completion date of 1/15/24 is still "On Target".

 

Has anyone else seen this issue in Workfront? 

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

2 replies

Madalyn_Destafney
Community Advisor
Community Advisor
February 2, 2024

Hi there, have your templates changed to be manual condition status? Here is more Condition info.

 

If this helped you, please mark correct to help others : )
KelseyF2Author
February 7, 2024

Hi, Our templates have not changed to manual. 

Lyndsy-Denk
Community Advisor
Community Advisor
February 5, 2024

Definitely check your Condition Type as Madalyn recommends.

Also, how much work are you folks processing in your instance? I learned recently that there's a limit for which the automatic timeline recalculation will process.

KelseyF2Author
February 7, 2024

Thank you for providing the link! I believe the amount of work we are processing is contributing to the issue.