Does anyone have experience or advice about using Workfront to store all scoped hours for the entire agency and then make them avaiable to use on projects? I'm looking for a functional solution that allows "deposits" and "withdrawals" like a bank.
- Import and store all scopes into Workfront in the form of planned hours (deposits).
- Create/plan projects as usual but have the planned hours in the project reduce the overall sum in the bank (withdrawals).
Thoughts on this
There would have to be a container of hours that are kept separate from the working projects. If the bank is a project then creating a custom status could work to filter it out of working project reports.
The bank project and the working project would have to be aware of each other so that their planned hours stay in sync, one drawing from the other in a zero sum fashion.
The solution would have to be reportable to track variance in scoped hours, project planned hours, and project actual hours.