Allow lag time for task relation type SF | Community
Skip to main content
March 16, 2018
New

Allow lag time for task relation type SF

  • March 16, 2018
  • 1 reply
  • 426 views

Currently Workfront does not allow lag time in a task relation type SF, e.g. I cannot input task relation "4sf-1d", as system prompts an error saying it does not accept negative value. However, this is industry standard that this task relation type must also work with lag time, not only lead time.

1 reply

April 4, 2018

this is a good idea..! hope we get it soon.