Is it possible to have the status of a project/task/issue to change AFTER approval or have some other event fire in WF?

Avatar

Level 2
 
2 Replies

Avatar

Level 4

@John Kane‚ Yes we have something like this set up in our instance. We have several custom project statuses that are implemented along the life of the project. We have certain tasks on our main project template that are milestone tasks that have approval processes on them. We have it set to where when those tasks statuses change to "Complete" (not complete-pending approval) the system automatically updates the status of the project to one of our custom statuses that we defined. I believe our IT used Fusion to accomplish this.

Avatar

Level 2

I wish automatic status update is available through the Approval process similar to how we can define in our approval which status to set on rejection.