Question
Duration Types and Task Constraints
I have been playing around with task constraints and duration types for our staffing needs. It seems like effort driven works well in the sense that I put in the planned start date and the planned completion date and it calculates the planned hours. We only assign 1 resource per task. So if I wanted someone to work 100% on a project from 7/1 to 7/31, I can put in those dates and it calculated the planned hours automatically. Our other scenario is that same resource may be only 50% allocated to that project in that duration. I would love to put the in the start and end dates and have it calc the planned hours to 84 hours (50% of 21 days * 8 hours). I have tried a bunch of settings but no avail. My other option is to use simple or calculatured assignment put in the start and end dates and manually do the math on the hours and plug them in the planned hours field. John Hoebler Cross Country Consulting