Hi there,
Is there a way or a workaround to duplicate a program that contains the same projects that are updated on a quarterly timeline?
Solved! Go to Solution.
Topics help categorize Community content and increase your ability to discover relevant content.
Views
Replies
Total Likes
Unless you use Fusion it's manual steps - duplicate the program, rename it, then copy each project, and finally bulk edit all copies and change to the new program.
Views
Replies
Total Likes
As far as I believe there is no option 'Copy' for Program object. This could be possible through Fusion automation..
Views
Replies
Total Likes
Unless you use Fusion it's manual steps - duplicate the program, rename it, then copy each project, and finally bulk edit all copies and change to the new program.