Duplicate a Program

Avatar

Level 1

Hi there,

 

Is there a way or a workaround to duplicate a program that contains the same projects that are updated on a quarterly timeline?

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

2 Replies

Avatar

Level 5

As far as I believe there is no option 'Copy' for Program object. This could be possible through Fusion automation..

Avatar

Community Advisor

Unless you use Fusion it's manual steps - duplicate the program, rename it, then copy each project, and finally bulk edit all copies and change to the new program.